As reported last week the Barker and Stonehouse project timeline target was 4 working days, which included 2 days for removal and preparation followed by a 2 day installation and commissioning process. As planned, the lift was handed back to the client for some minor making good before the end of day 4. This new platform lift will give years of service to the store and their customers!